Hwy 212 & Morningside Construction
- Construction begins May 6, 2024
- Construction ends Sept. 13, 2024 (updated from Aug. 30 due to weather)
- Dates are weather dependent and subject to unforeseeable circumstances.
Project update
Aug. 23, 2024
- Crews have continued with concrete work.
- Next up: finish up concrete work, work on overhead signs, grading, and placing topsoil.
- Construct a single lane roundabout at the intersection of Hwy 212 and Morningside Ave. in Glencoe.
- Project includes adding a multi-use trail on all sides to connect to existing trails in the area.
Airport Terminal Building Construction
June 20, 2023 Update – Framing is underway at the airport today!
Housing Study
WSB is in the process of developing a housing study for Glencoe. The last housing study was completed in 2017. Once complete, this document will outline the existing needs for housing within the City and be a tool for developers looking to build in Glencoe.
Oscar Olson Park Study
SEH is in the process of developing a study for Oscar Olson Park. This will identify priorities for current and future uses within the park as well as a layout for amenities. Community input from the Comprehensive Plan will be used to identify those priorities for the park. If you have thoughts on Oscar Olson Park please contact Mark Larson at [email protected].
Questions/Concerns?
Do you have questions/concerns regarding restoration or project details? Please follow the instructions below:
- The resident/business should call into Nuvera call center at 844-354-4111.
- The associate will take your contact information, specific address, and call back number.
- The information will be routed to the OSP construction department and contractors for follow-up.